After the kick-off meeting, it was decided that were going to be 2 weekly meetings with ech of the supervisors:

 

  • EDP: every Thursday at 14H30

  • FEUP: every friday at 14H15

 

 

Every month there will be a meeting with both supervisors, to discuss the work developed so far and to plan the next steps.

 

Work time

The figure below ilustrates the time spent in each work phase, described in the stretegy section (click on image to enlarge).

Work progress
  • 24/Feb to 2/March:

      -  24/Feb: kick-off meeting;

      -  Reading applicable regulation (RQS 2013 and Incident Classification          Guide);

      -  Start research;

      

  • 3/March to 23/March

     -  Incident database validation;

      -  MV undeground network database validation;

      -  Biography research.

      

  • 24/March to 30/March

      -  Decision to exclude incidents caused by external entitties and programed interruptions;

      -  Incident database validation;

      -  Biography research.

      

  • 31/March to 6/April

      -  Characterizing the MV underground network (data analysis);

      - Underground network incident's behaviour;

      -  Biography research.

 

  • 7/April to 13/April

      -  7/April: meeting in the department of network studies to show results;

      -  8/April: Monthly meeting with supervisors;

      -  Continue underground network behaviour study;

      -  Continue biography research.

 

  • 14/April to 27/April

      -  Corrections based on the meetings;

      -  Failure rate calculation;

      -  Continue  characterizing the MV underground cable behaviour;

      -  24/April: meeting with DTI;

      -  Continue validating  MV underground network database;

   

  • 28/April to 6/July

      -  Thesis structure revision;

      -  Continue validating  MV underground network database;

      -  Continue  cable failure analysis;

      -  Continue biography research;

      -  Failure rate analysis;

      - Start correlation analysis.

   

  • 7/July to 13/July

      -  Presentation preparation;

      -  7/July: Meeting in Lisbon to show results;

      -  Corrections based on the meeting.

  

  • 14/July to 31/August

      - Statistical analysis;

      - Thesis writting and revision.

 